I created a job chain in SQLEJM with a root job one server and a second job on a different server with the job chain scheduled hourly. The root job runs on schedule as expected. However, the second job defined in the chain does not run following completion of the root job in the chain. The second job will only run after completion of the root job when the chain is started within the SQLEJM console. Is this the only way to run the entire job chain based on the schedule?